RALEIGH, N.C. (AP) — Duke Energy says it plans to begin dredging coal ash out of a North Carolina river on Tuesday as the state's environmental agency moved to scuttle a previously proposed settlement with the company over pollution leaking from waste dumps at its power plants.

Lawyers for the N.C. Department of Environment and Natural Resources asked a judge late Monday to disregard its own proposed settlement with the nation's largest electricity provider. Under the deal, Duke would have paid fines of $99,111 for pollution that leaked from two coal dumps like the one that ruptured Feb. 2, spewing out enough toxic sludge into the Dan River to fill 73 Olympic-sized pools. The deal proposed over the summer covered plants near Asheville and Charlotte, while this month's spill was near the town of Eden.

The state dumped the settlement one day after a story by The Associated Press in which environmentalists criticized the arrangement as a sweetheart deal aimed at shielding Duke from far more expensive penalties the $50 billion company might face under the federal Clean Water Act.

The settlement would have required Duke to study how to stop the contamination, but included no requirement for the company to actually clean up the dumps near Asheville and Charlotte.

"DENR asks this court to hold in abeyance any further consideration of the proposed consent order while DENR undertakes a comprehensive review of all North Carolina coal ash facilities in view of the recent coal ash release into the Dan River," said the state's letter to Wake County Superior Court Judge Paul Ridgeway, a copy of which was obtained by the AP.

Drew Elliot, a spokesman for the state environmental agency, declined to comment.

Duke Energy spokeswoman Tammie McGee said it is the company's policy not to comment on pending litigation.

On the afternoon of Feb. 2, a security guard patrolling the grounds of Duke's Dan River Steam Station discovered that a pipe running under a 27-acre toxic waste pond had collapsed. The company reports that up to 82,000 tons of coal ash mixed with 27 million gallons of contaminated water drained out, turning the river gray and cloudy for miles. The accident ranks as the third-largest such coal ash spill in the nation's history.

The public was not told about the breach until the following day and initial reports provided by Duke and DENR did not make clear the massive scale of the disaster. It took six days for the company to finally seal the pipe.

State regulators initially said testing showed levels of arsenic, lead and other toxic contaminates in the river water were at levels low enough to be safe for both fish and humans. On Sunday, however, the state officials admitted they had made an "honest mistake while interpreting the results" and issued an advisory warning people to avoid prolonged contact with the water.

Duke said Monday it plans to start cleaning out a small section of the river nearest to the spill site.

"We're going to use big vacuum hoses and a vacuum truck to pull that ash out," said Paige Sheehan, a company spokeswoman. "It will help us better inform our long-term plan and test out a particular technique to see if it's effective. It's a long-term process. We won't be able to do this overnight. But we will be here until the job is done."

Duke issued a public apology for the spill last weekend and said it would be accountable for cleaning up its mess.

AP reported Sunday that environmental groups have tried three times in the past year to use provisions under the Clean Water Act to sue in federal court to force Duke to clear out leaky coal ash dumps.

The groups sued after North Carolina regulators failed to act on evidence conservationists gathered of groundwater contamination.

Each time, the state agency blocked the citizen lawsuits by intervening at the last minute to assert its own authority under the act to take enforcement action in state court. After negotiating with the company, the state proposed settlements that environmentalists regarded as highly favorable to the company.

Clean water advocates have long complained that state regulators are too cozy with the polluters they regulate. But they say the relationship appears to have grown closer since the January 2013 inauguration of Gov. Pat McCrory, a Republican who worked at Duke Energy for 28 years.

Since his unsuccessful first campaign for governor in 2008, campaign finance reports show Duke Energy, its political action committee, executives and their immediate families have donated at least $1.1 million to McCrory's campaign and affiliated groups that spent on TV ads, mailings and events to support him.

After winning in 2012, McCrory appointed Raleigh businessman John Skvarla to head the state environmental agency charged with policing his former employer. Skvarla has described his agency's role as being a "partner" to those it regulates, whom he refers to as "customers."

Lawyers for the environmental groups who had tried to sue Duke in federal court were shut out of the negotiations between state regulators and the company that produced the now scuttled settlement proposal. They had hoped to convince the state judge overseeing the case to reject the deal.

Frank Holleman, a senior attorney at the Southern Environmental Law Center, worried that Monday's about-face might be just another tactic by the state to help Duke avoid paying for the harm it has done to the North Carolina's rivers and lakes.

"They are reacting to the public heat," Holleman said. "The spill at Dan River has shown that the entire path they have taken — not enforcing the law effectively as to coal ash — is a political embarrassment and a disaster for clean water in North Carolina. They are scrambling to figure out what to do without losing face."

 
 

Article Comments

No comments posted for this article.
 
 

Post a Comment

You must first login before you can comment.

*Your email address:
*Password:
Remember my email address.
or
 
 

 

I am looking for:
in:
News, Blogs & Events Web
 
 

Blog Photos

Amy Adams, North Carolina campaign coordinator with Appalachian Voices dips her hand into the Dan River in Danville, Va. as signs of coal ash appear in the river. Duke Energy estimates that up to 82,000 tons of ash has been released from a break in a 48-inch storm water pipe at the Dan River Power Plant in Eden N.C. Over the last year, environmental groups have tried three times to use the federal Clean Water Act to force Duke Energy to clear out leaky coal ash dumps. Each time, the N.C. Department of Environment and Natural Resources has effectively halted the lawsuit by intervening at the last minute to assert its own authority to take enforcement action. In two cases, the state has proposed modest fines but no requirement that the nation’s largest electricity provider actually clean up the coal ash ponds. The third case is pending. (AP Photo/Gerry Broome)

 
 
 
 

Blog Links